Seal-coating Weather & Drying Time.
The all time favorite question: How long does it take to dry??
Let’s talk weather first.
Weather Conditions:
- Sealer should not be applied unless pavement temperature is at least 50F° (10C°) and the air temperature is 50F° (10C°) and rising.
- Sealer should not be applied during rainy or wet weather, or when rain is anticipated within eight hours after application is completed.
- Sealer should not be applied to hot surfaces under the summer sun (over 90F°, ambient) without first cooling the surface with clean water. Water should dampen the surface without leaving puddles.
- Since an emulsion may be damaged by freezing, it should be protected at all times when the temperature drops below 40F° (4C°).
Drying Time:
The final coat must be allowed to dry a minimum of eight hours of good daylight drying conditions before opening to traffic, and initially cure enough to drive over without damage to the sea-lcoat.
If marginal weather conditions exist during this eight hour drying time, additional time will be required. In some cases this could exceed 24 hours.
Check the surface after this for traffic-ability before opening it to vehicle traffic.